Hi All, On Friday 3/14, there will be no parking on most of Watts Street from 7AM-3PM. The town of Chelsea will likely be towing during this time, so please have your cars parked elsewhere! Thank you and sorry for the inconvenience.
Starting Thursday 1/30, the city will begin to do their work on replacing curbs on Watts street and Central Ave. This work is expected to take roughly a month. During this time, the city will be implementing parking closures around the building. Please be on the lookout for parking areas to be affected beginning Thursday, January 30th.
The jobsite will be open tomorrow, 11/23. Regarding next week, the jobsite will be closed from 11/28 through 12/1 for Thanksgiving. The jobsite will re-open on Monday, 12/2. Have a great Thanksgiving!
The jobsite will be open on 11/16/24. Please note, Building B is turned over at this point and occupied by residents. Building A is still under construction. If interested in leasing, please visit the below website or walk into the leasing office some day! https://www.duoapts.com/
All - the jobsite will be open on Saturday and Monday, 11/11 of this week. Building B at this point is operational, so all work will be coming from Building A. Have a nice weekend.
Trucking was delayed last week due to a few conditions on site, but trucking is now beginning today and will last roughly 2 weeks on streets neighboring the Chelsea Innes Project (Watts and Willow primarily).
Please be aware that trucking on Watts Street will be continuing in the coming week. Please expect delays and closures on Watts accordingly. The jobsite will be open tomorrow 9/28 for the duration of the work day. Have a nice weekend all!