10/2/24 - Midweek Trucking Update

Trucking was delayed last week due to a few conditions on site, but trucking is now beginning today and will last roughly 2 weeks on streets neighboring the Chelsea Innes Project (Watts and Willow primarily).

9/27/24 - Trucking Continues

Please be aware that trucking on Watts Street will be continuing in the coming week. Please expect delays and closures on Watts accordingly. The jobsite will be open tomorrow 9/28 for the duration of the work day. Have a nice weekend all!

9/20/2024 Lookahead

Few things to note coming up: The jobsite will be open on 9/21 During the week of 9/23 Watts and Willow will have increased trucking traffic. Dependent on the Chelsea PD, these streets may be temporarily closed at times There are parking spots now opened up towards the end of Watts for resident's use Thank you all!

9/13/24 Weekend Schedule

The jobsite will be open on 9/14/24

9/6/2024 Weekend Lookahead

The jobsite will be open on 9/7.  Building B remains on track for a fall of 2024 opening. We are getting close!

8/23/2024 Weekend Schedule

The jobsite will be open on Saturday 8/24/2024. Schedule remains on track for a fall delivery of Building B. Building A remains on track as well.

8/16/2024 Weekend Schedule

The jobsite will be open on Saturday 8/17/2024. Have a nice weekend everybody.

Chelsea Innes - 8/9/2024 Update

The jobsite will be open on Saturday 8/10/2024. Have a nice weekend everyone.

Chelsea Innes - 7/26/24 Lookahead

The jobsite will be open on Saturday 7/27. Additionally, please note that Watts street will be closed on August 1st due to construction related activities. We apologize for any inconvenience.  The Chelsea Innes project is still on track for a fall of 24 delivery date for Building B.

7/12/2024 Weekend Schedule

Please note that the jobsite will be open on Saturday, July 13th. Have a nice weekend everybody!

7/3/24 Watts Closure

All, please be aware that Watts Street will be temporarily closed off on Wednesday, July 3rd. Thank you and have a great Fourth of July!

6/28/2024 - Chelsea Innes Lookahead

The Chelsea Innes Redevelopment remains on track for a Building B completion in early Fall 2024. Finishes are going in and the units are looking great! Looking forward to welcoming back previous residents and welcoming new ones as well! Lookahead for this weekend: The jobsite will be open on Saturday 6/29/2024. Lookahead for this coming week: Willow Street will be temporarily  closed  on Wednesday July 3rd for a concrete pour. The road will open again as soon as the concrete pour is finished. The jobsite will be closed 7/4 through 7/7. The jobsite will open again on Monday 7/8. Happy Fourth of July!