3/15/23 Three Week Look Ahead

 



PHASE 1 | BLDG C EARTHWORK - COMPLETE  

PHASE 2 | BLDG B EARTHWORK Thu 9/15/22 - Mon 9/25/23

Bldg B | Earthwork Prep Thu 9/15/22 - Wed 4/5/23

    Ground Improvement Layout & Mobilization Mon 3/20/23 - Fri 3/24/23

    Ground Improvement Installation Mon 3/27/23 - Wed 4/5/23

PHASE 3 | BLDG A EARTHWORK Wed 10/12/22 - Wed 11/1/23

GARAGE FOUNDATIONS COMPLETE BY Tues 3/28/23

PRECAST GARAGE ERECTION STARTING Thurs 4/6/23

______________________________________________________

What will you see? 

Ground Improvements: Please visit this link to watch a video on the Rammed Aggregate Piers: Rammed Aggregate Pier 

Precast Parking Garage Erection: Please view video of another project's garage erection to see a time lapse of the process: 