3/15/23 Three Week Look Ahead
PHASE 1 | BLDG C EARTHWORK - COMPLETE
PHASE 2 | BLDG B EARTHWORK Thu 9/15/22 - Mon 9/25/23
Bldg B | Earthwork Prep Thu 9/15/22 - Wed 4/5/23
Ground Improvement Layout & Mobilization Mon 3/20/23 - Fri 3/24/23
Ground Improvement Installation Mon 3/27/23 - Wed 4/5/23
PHASE 3 | BLDG A EARTHWORK Wed 10/12/22 - Wed 11/1/23
GARAGE FOUNDATIONS COMPLETE BY Tues 3/28/23
PRECAST GARAGE ERECTION STARTING Thurs 4/6/23