3/23/23 Three Week Look Ahead
EARTHWORK 9/6/22-11/21/23
PHASE 1 | EARTHWORK 9/6/22-6/29/23
Bldg C | Building Earthwork 2/3/23-6/29/23
PHASE 2 | BLDG B EARTHWORK 9/15/22- 9/26/23
Bldg B | Ground Improvement Installation Mon 3/20/23 Wed 3/29/23
PHASE 3 | BLDG A EARTHWORK 10/12/22-11/21/23
CONCRETE 2/3/23-6/17/24
PHASE 1 | BLDG C CONCRETE Fri 2/3/23 Tue 7/11/23
Bldg C | Foundations Fri 2/3/23 Thu 4/6/23
PHASE 2 | BLDG B CONCRETE Wed 3/29/23 Tue 1/30/24
Bldg B | Foundations Wed 3/29/23 Fri 6/16/23
PRECAST CONCRETE Tue 3/28/23 Mon 7/10/23
PHASE 1 | BLDG C PRECAST Tue 3/28/23 Mon 7/10/23
*Crane to be built 4/10. The crane will erect the precast parking garage for a duration of 6 weeks.