4/10/23 3 Week Look Ahead
What you will see:
- 4/13/23 Crane Erection for Phase 1
- Precast parking garage erection 4/13/23-3/31/23
- Please anticipate road closures. Willow Street between Watts Street and Central Ave. to be closed Monday-Friday 7 AM to 3 PM.
- Phase 2 - Concrete foundations ongoing
- Phase 3 - Ground Improvements start of May
- Steam tunnel removal with negative pressure containment 4/10/23-4/17/23
Upcoming Events:
- April 19th 4:30 PM - 6:30 PM Real Estate and Construction Opportunity Fair at the Jordan Boys and Girls Club