4/10/23 3 Week Look Ahead

 








What you will see:

  • 4/13/23 Crane Erection for Phase 1
  • Precast parking garage erection 4/13/23-3/31/23 
    • Please anticipate road closures. Willow Street between Watts Street and Central Ave. to be closed Monday-Friday 7 AM to 3 PM. 
  • Phase 2 - Concrete foundations ongoing
  • Phase 3 - Ground Improvements start of May
    • Steam tunnel removal with negative pressure containment 4/10/23-4/17/23
Upcoming Events:
  • April 19th 4:30 PM - 6:30 PM Real Estate and Construction Opportunity Fair at the Jordan Boys and Girls Club