4/21/23 3 Week Look Ahead
PHASE 1 | BLDG C CONCRETE 2/3/23-7/17/23
PHASE 2 | BLDG B CONCRETE 3/28/23-2/5/24
Bldg B | Foundations 3/28/23-6/22/23
PHASE 1 | BLDG C PRECAST
Precast Erection 4/14/23-5/30/23
*Please note that starting May 1, the jersey barriers will be moved, and parking will be available up against the jersey barriers in striped locations.
*Also starting May 1, ground improvements commence across Phase 3. This will result in vibration and sound. The development team has enlisted a third party consultant to monitor vibrations as well as oversee the activities.
All Abatement and Demolition Activities are Complete.