4/28/23 Three Week Look Ahead

 

PHASE 1

Precast Erection - Ongoing until May 30, 2023

*Willow Street between Watts and Central closed Monday-Friday 7 AM- 3PM until May 30, 2023


PHASE 2

Foundation Work ongoing


Phase III

Ground improvements to start 5/8. 


Parking updates to follow Traffic Commission Hearing 5/2. Jersey barriers to be moved May 4. 