4/28/23 Three Week Look Ahead
PHASE 1
Precast Erection - Ongoing until May 30, 2023
*Willow Street between Watts and Central closed Monday-Friday 7 AM- 3PM until May 30, 2023
PHASE 2
Foundation Work ongoing
Phase III
Ground improvements to start 5/8.
Parking updates to follow Traffic Commission Hearing 5/2. Jersey barriers to be moved May 4.