6/1/23 Three Week Look Ahead
Phase I (Building C Parking Garage Garage)
Underslab Utilities 6/1/23-6/30/23
Phase II (Building B)
Foundations and underslab utilities underway
Steel erection starting 6/23/23
Phase III (Building A)
Foundations and Footings formwork underway with concrete pours ongoing