3 Week Look Ahead

SITEWORK

- Ground improvements to be complete by Monday, August 28

-Foundations ongoing on the western side of the project site


WOOD FRAME

PHASE 2 | BLDG B WOOD FRAME

2nd Floor Walls/Trusses - Complete 

3rd Floor Walls/Trusses 11 days starting Wed 8/23/23

4th Floor Walls/Trusses 11 days starting Fri 9/8/23


CONCRETE MASONRY UNIT 96 days 

Elevator Shaft 4 & 5 2 wks starting Wed 8/16/23