3 Week Look Ahead
CONCRETE
Building A foundations to be complete by Mid October
STEEL
BLDG A STRUCTURAL STEEL Tue 10/3/23 Thu 11/30/23
Zone A-1| Block C: Level 1 (+/- 13,700 SF) 10/3/23-10/27/23
Mobilization 10/3/23 -10/4/23
Steel Erection 10/5/23 - 10/10/23
Steel Leveling/Squaring/Welding 10/11/23 -10/17/23
WOOD FRAME
BLDG B WOOD FRAME
Block A | Cubes 1 & 2 Mon 8/7/23 - 10/27/23
4th Floor Walls/Trusses 9/15/23 - 9/27/23
5th Floor Walls/Trusses 9/28/23 - 10/10/23
6th Floor Walls 10/11/23 - 10/17/23