 CONCRETE

    Building A foundations to be complete by Mid October

STEEL

BLDG A STRUCTURAL STEEL Tue 10/3/23 Thu 11/30/23

    Zone A-1| Block C: Level 1 (+/- 13,700 SF) 10/3/23-10/27/23

    Mobilization 10/3/23 -10/4/23

    Steel Erection 10/5/23 - 10/10/23

    Steel Leveling/Squaring/Welding 10/11/23 -10/17/23


WOOD FRAME

BLDG B WOOD FRAME 

Block A | Cubes 1 & 2 Mon 8/7/23 - 10/27/23

    4th Floor Walls/Trusses 9/15/23 - 9/27/23

    5th Floor Walls/Trusses 9/28/23 - 10/10/23

    6th Floor Walls 10/11/23 - 10/17/23