Please see below for the updated lookahead schedule:

  • BLDG A Structural Steel: Complete
  • BLDG A Elevator Shaft: 1/10/2024 - 1/23/2024
  • BLDG A, Block C, Wood Frame: 11/8/2023 - 2/5/2024
  • BLDG B Wood Frame: 8/7/2023 - 1/5/2024
  • BLDG B MEP Rough: 9/21/2023 - 4/19/2024

Please note, the jobsite will be open on 1/6/2024.